U.S. Steel — Ecorse ASU
A large air separation unit on an older design, held for an extended period, then returned at full speed to serve a steel operation.
- Location
- Ecorse, Michigan
- Industry
- Industrial gas / steel supply
- Project type
- Air separation unit
- Role
- Project Controls Engineer
- Lifecycle phase
- Restart & recovery planning
- Career stage
- White Martins / Praxair — Project Controls
Restarting a project is not the same as resuming a schedule
Context
The project had remained on hold for an extended period before returning at full speed, creating a recovery environment rather than a continuation.
The execution problem
The existing baseline and its assumptions no longer described execution reality — supplier status, design vintage, resources and sequence had all moved.
Approach
Re-planning against current conditions rather than reactivating a historical baseline, followed by contractor coordination and progress control aligned to the revised path.
A project returning from a long hold must be replanned against today's reality, not simply restarted from yesterday's baseline.