Skip to content
← Selected projects

Votorantim Siderurgia — Front-End Development & CAPEX portfolio

Front-end project development inside a capital-investment process serving operating steel plants, where technically valid projects still competed for finite capital.

Location
Brazil · Argentina · Colombia
Industry
Steel
Project type
Capital portfolio / front-end development
Role
Investment Analyst — CAPEX
Lifecycle phase
Front-end definition & investment governance
Career stage
2008 – 2010

Turning operating needs into fundable, comparable investments

Context

Operating issues, safety requirements, reliability needs and growth opportunities arrived from operators and plant managers as problems, not as projects.

Approach

Each need was converted into a defined project: scope, WBS, cost, schedule, risk, CAPEX/OPEX treatment and expected return, at a level of definition sufficient for management decisions.

Monthly portfolio reviews compared both value and level of definition. Projects with stronger returns, clearer scope and higher definition moved forward for prioritization and strategic planning.

Value Improving Practices were applied as a habit of challenge — improving the investment proposition, not only the design.

Range of the portfolio

Sustaining and reliability work such as electrical modernization of substations feeding operating facilities; production-improvement projects on process equipment; and growth cases such as evaluating a rebar cut-and-bend operation, including equipment manufacturers and regional location strategy.

A good idea does not become a good investment until its scope, value and uncertainty can be understood.